M&S Regional Distribution Centre – Enfield

Sector: Food Storage & Distribution
ISD Division: Coldstores
Duration of Project: 24 weeks
Project Value: £1.7m

ISD-Solutions- Cold-storage-Construction-MS-Enfield-3558

 

 

 

 

Project

ISD Solutions were awarded the contract to design and build 2 large chambers at the Regional Distribution Centre for leading retail brand Marks & Spencer.

The project itself demanded a fast installation in order to complete prior to the commercially sensitive festive period.

ISD designed and built Chamber A 110m x 60m x 5.5m high and Chamber B 100m x 60m x 6m high.

This project included fire shutters fitted to steel framework designed and installed by ISD in order to maintain a 2 hour fire rated blockwork partition wall, Rapid Roll doors and numerous personnel doors.

 

 

 

 

 

To this project ISD installed 40No dock pods approx. 6m x 3m x 3m high. This new build will be used for distributing goods between the M&S stores throughout greater London.

Products used:-

Personnel Doors from Scott Doors & ISD Solutions & Bluseal

Rapid roll doors/ Fire shutters from Efaflex

Polyisocyanurate panels from Kingspan

Mineral fibre panels from Eurobond

CAT Ladders from Kingswinford Engineering

Trims/ Plating from ISD Solutions

ISD’s expertise in Fire Rated construction was called upon during the construction to specify and install firewalls separating the warehouse units. Fire rated doors and windows were also supplied and installed by ISD.

Main Contractor Testimonial

“I recently worked with ISD on a Warehouse refurbishment which upgraded a 30 year old ambient warehouse to a 2 chamber refrigeration store for M&S in North London. This was my first time working with ISD and I found ISD & Justin Groome particularly to be a valuable well knowledgeable sub contractor to have on a project such as this, Justin himself co-ordinated the project well ensuring all design information, labour and materials were all onsite on time and delivered in a quality fashion.

I dealt with Justin on a daily basis and found him to be extremely helpful and as eager as myself to deliver a quality job on time and safely with his approach to H&S to be the high standard that Winvic expect.

The finished article delivered by ISD was of superb quality and look forward to working with them again on a future project.”

Anthony Nelson

Project Manager – Winvic

 

 

 

 

 

 

Jason Carter